Campus Facility Services Records, 1969-2008, Preliminary Inventory
Campus Facility Services Records, 1969- 2008
Preliminary Inventory
UA- 066
Qty.: 17.8 c.f. (17 Cartons 2 Document Boxes)
ABSTRACT
In 1972 the Buildings Services Department reported to the Vice Chancellor/Dean for Administrative Affairs. Later, the department came under the supervision of the Director of Physical Plant. By 1992, the department was named Campus Facilities Services and reported to the Vice Chancellor for Administration.
Records include operation and maintenance manuals for buildings and building equipment for various campus buildings.
ACCESS
Personnel and student records and other personal information in these records are restricted. All other material is open to the public without restriction. Copyright laws of the
PREFERRED CITATION
Cite as: Campus Facility Services Records, Ruth Lilly Special Collections and Archives, University Library,
ACQUISITION
Accessions: A1997/98-013, A2006/07-028, A2010/11-008.
COLLECTION STATUS
This preliminary inventory serves as an interim guide to the described records. A finished finding aid based on final appraisal and arrangement of the records of this university unit will be prepared at a future date.
Contents | Box | |
Nuclear Medicine Facility- Radiology, | 1 | |
| Index, 5/26/1978 |
|
| Panels, 10/31/1975 |
|
| Dimming, 1969 |
|
| Light Fixtures, 11/11/1976 |
|
| Fire Alarm, 2/21/1978 |
|
| Duct Detectors, undated |
|
| Nurse Call System, 2/10/1977 |
|
| Clock System, 10/5/1976 |
|
IU Hospitals |
| |
| Installation of Automatic Engine/ Generator Synchronizing & Paralleling Equipment, #852-1975, 3/25/1985 |
|
| Central Medical Air System Revision, #854-2044, undated |
|
| ||
Science & Engineering Technology Phase II, #855-2110 |
| |
| AHU-2-E [apparatus test report] 12/1991 |
|
| AHU-2-W [air & water test & balance report] 10/1992 |
|
| AHU-3-E [apparatus test report] 12/1991 |
|
| AHU-3-W [apparatus test report] 12/1991 |
|
| EE-1 to EE-10 [apparatus test report] 12/1991 |
|
| Coil Data Sheets, undated |
|
| EF-1 to EF-2 [Diffuser & Grill Test] 12/1991 |
|
| Electrical Maintenance- Intro, 1992-1994 |
|
| Electrical Maintenance- Switchgear, 3/28/1990 |
|
| Electrical Maintenance- Panel Boards, 125/1989 |
|
| Electrical Maintenance - Busduct, 4/1990 |
|
| Electrical Maintenance- Adjustable Frequency Controller |
|
| Electrical Maintenance- Computer Isolation Transformer |
|
| Electrical Maintenance- S & C Switch, 1989 |
|
| Electrical Maintenance- Lighting Control, undated |
|
| Hoods, undated |
|
| Water Balance, 5/1992 |
|
| Heating, 10/1992 |
|
| General |
|
| Section 1- 21 |
|
| Section A- G |
|
| General |
|
| ||
| Index, 12/1988 |
|
| Section 1- 4 |
|
| Section 5- General |
|
| Section 5- Panel Board & Motor Control |
|
| Section 5- Conduit, Fittings & Cable |
|
| Section 5- Light Fixtures & Lamps |
|
| Section 5- Consolidated Lighting Inc. |
|
| Section 5- Bryant Devices & Floor Outlets |
|
| Submittal to Keith Electrical Intercom/ Paging System |
|
Clinical Building # 859-2233, 3/24/1986 |
| |
Coleman Hall #859-2235 Plumbing & Heating Section, ca. 1985 |
| |
| Index |
|
| Valve Chart |
|
| Unit Ventilator |
|
| Sheet Metal |
|
| Temperature Control |
|
| Plumbing & Medical Equipment |
|
Institute for Psychiatric Research, HVAC Alterations- IU Hospital #865-2443, ca. 1986 |
| |
| Forward |
|
| Index |
|
| Balance Report, 9/24/1987 |
|
| FEBCO Backflow Preventer |
|
| TACO Circulation Pumps, 1986 |
|
| TACO Circuit Setters, 5/1/1981 |
|
| Grinnell Valves | 2 |
| Armstrong Pipe Insulation, 9/3/1986 |
|
| International Fan Coil Units, 7/22/1986 |
|
| Johnson Controls- Temperature Controls, 10/21/1986 |
|
Medical Records Relocation #877-2731, ca. 1987 |
| |
| Contractors/ Suppliers |
|
| CDI (Construction Dynamics, Inc.) Field Reports, 1988-1989 |
|
| Architect/ Owner Correspondence, 1988-1989 |
|
| Thermal & Moisture Protection, 7/1988 |
|
| Doors & Windows, 7/18/1988 |
|
| Finishes, 8/1988 |
|
| Specialties, 1988 |
|
| Mechanical, 8/1988 |
|
| Electrical, 8/1988 |
|
| Wood & Plastics, 8/1988 |
|
| [Record Manual] 2/24/1988, 1-3, A-C |
|
Radiologic/ Physics Renovation # 879-2823, ca. 1987 |
| |
| Index |
|
| Unistrut Indianapolis, 6/25/1990 |
|
| Gate Company- Kelmar Traffic Decks |
|
|
| |
|
| |
| Window Replacement, 1990 |
|
| Contract Hardware & Specialties, 1990 |
|
| Glazed Tile Walls |
|
| Gates Company- EMBE Composition floors |
|
| Commercial Flooring |
|
| B & E Painting, 1990 |
|
| Chalkboards & Tackboards |
|
| Accurate Partitions- Toilet Partitions |
|
| Tate Access Floors |
|
| Medart Lockers |
|
| Washroom Accessories |
|
| Draper Shade & Screen- Protection Screens |
|
| Darkroom Door |
|
| Horizontal Aluminum Blinds |
|
| Project Manual |
|
Psychiatric Research Animal Quarters Upgrade #881-2914, ca. 1988 |
| |
| General, 4/18/1989 |
|
| Plumbing- Section 1 |
|
| Insulation- Section 2 |
|
| HVAC- Section 3 |
|
| Fan Coil Units- Section 4 |
|
| Tempmaster VAV Boxes- Section 5 |
|
| Anemostat- Section 6 |
|
| Ventilation - Section 7 |
|
| Roof Exhauster- Section 8 |
|
| Prefabricated Curbs- Section 9 |
|
| Humidifier- Section 10 |
|
| Duct Accessories- Section 11D-E |
|
| Valves- Section 12 |
|
| Titus Constant Volume Boxes- Section 13 |
|
| Johnson Controls- Section 14 |
|
| ||
| Index |
|
| Section A- H |
|
| Section I | 3 |
| Warranties |
|
Medical Science- Biochemistry Lab/Office Remodeling, #886-3058, ca. 1988 |
| |
| General- Mechanical, Book 1 |
|
| Section A- I, Book 1 |
|
| Warranties & Valve Chart, Book 1 |
|
| General-Mechanical, Book 1a |
|
| Section A-B, Book 1a |
|
| Precision Control Maintenance, Book 1a |
|
| Section C- I, Book 1a |
|
| Warranties & Valve Chart, Book 1a |
|
| Index, Book 2 |
|
| Asbestos Removal, Book 2 |
|
| Finish Selection, Book 2 |
|
| Selective Demolition, Book 2 |
|
| Masonry, Book 2 |
|
| Metal Fabrication, Book 2 |
|
| Rough Carpentry, Book 2 |
|
| Architectural Woodwork, Book 2 |
|
| Insulation, Book 2 |
|
| Joint Sealers, Book 2 |
|
| Steel Frames, Book 2 |
|
| Flush Wood Doors, Book 2 |
|
| Folding Doors & Partitions, Book 2 |
|
| Finish Hardware, Book 2 |
|
| Glass & Glazing, Book 2 |
|
| Gypsum Drywall, Book 2 |
|
| Acoustical Ceiling, Book 2 |
|
| Terrazzo, Book 2 |
|
| Resilient Flooring, Book 2 |
|
| Carpeting, Book 2 |
|
| Special Coating, Book 2 |
|
| Painting, Book 2 |
|
| Marker Boards & Tack Boards, Book 2 |
|
| Signage, Book 2 |
|
| Fire Extinguishers & Accessories, Book 2 |
|
| Accessories, Book 2 |
|
| Laboratory Fume Hood, Book 2 |
|
| Window Treatment, Book 2 |
|
| Mechanical, Book 2 |
|
| Electrical, Book 2 |
|
| Index, Book 2a |
|
| Asbestos Removal, Book 2a |
|
| Finish Schedule, Book 2a |
|
| Selective Demolition, Book 2a |
|
| Unit Masonry, Book 2a |
|
| Metal Fabrications, Book 2a |
|
| Rough Carpentry, Book 2a |
|
| Architectural Woodwork, Book 2a |
|
| Insulation, Book 2a |
|
| Joint Sealers, book 2a |
|
| Steel Frames, Book 2a |
|
| Flush Wood Doors, Book 2a |
|
| Folding Doors & Partitions, Book 2a |
|
| Finish Hardware, Book 2a |
|
| Glass & Glazing, Book 2a |
|
| Gypsum Drywall, Book 2a |
|
| Acoustical Ceiling, Book 2a |
|
| Terrazzo, book 2a |
|
| Resilient Flooring, Book 2a |
|
| Carpeting, Book 2a |
|
| Special Coating, Book 2a |
|
| Painting, Book 2a |
|
| Marker Boards & Tack Boards, Book 2a |
|
| Signage, Book 2a |
|
| Fire Extinguisher & Accessories, Book 2a |
|
| Accessories, Book 2a |
|
| Laboratory Fume Hoods, Book 2a |
|
| Window Treatment, Book 2a |
|
| Fire Protection Piping, Book 2a |
|
| Mechanical, book 2a |
|
| Electrical, book 2a |
|
Medical Science- Chilled Water Service, #888-3113, ca. 1988 |
| |
| Index |
|
| Map |
|
| Temperature Control |
|
Lecture Hall- Electronic Classroom Renovation, #891-3256, ca. 1989 |
| |
| Index |
|
| Material Supplier & Subcontractor List |
|
| Certificate of Substantial Completion |
|
| Warranties |
|
| Metal Fabrication |
|
| Finish Carpentry/ Millwork |
|
| Doors & Hardware |
|
| Acoustic Wall System |
|
| Floor Covering |
|
| Painting |
|
| Miscellaneous Specialties |
|
| Equipment/ Furnishings |
|
| ||
| Index, 1991 |
|
| Miscellaneous |
|
| Architectural, 1990-1991 |
|
| Processing Equipment, 1989 |
|
| Equipment, 1991 |
|
| Mechanical, 1991 |
|
| Electrical |
|
| Drawings |
|
Medical Science- Anatomy Lab/ Office Remodel, #898-3415 |
| |
| Index |
|
| Valves- Section A |
|
| Ventilation - Section B |
|
| Mechanical Insulation- Section C |
|
| Pipes & Tubes- Section D |
|
| Drains- Section E |
|
| Plumbing- Section F |
|
| Water Cooler, |
|
| Steam/ Piping- Section H |
|
| Humidifiers- Section I |
|
| Industrial Thermometers- Section J |
|
| Fans, Ducts, Grills- Section K |
|
| Johnson Controls, Inc.- Section L |
|
| “Isomix” Constant Volume Coil- Section M |
|
| Pumps- Section N |
|
| Air & Hydronic Distribution Systems- Section O |
|
| Warranties |
|
| Valve Chart & Map |
|
| Index, Book 2 |
|
| Fire Protection Sprinkler System |
|
| Section A- L, Book 2 |
|
| Section N- O, Book 2 | 4 |
| Warranties, Book 2 |
|
| Valve Chart & Map, Book 2 |
|
| Electrical- Raceways |
|
| Electrical- Light Fixtures |
|
| Electrical- Devices/ Plates |
|
| Electrical- Motor Starters |
|
| Electrical- Disconnects |
|
| Electrical- Transformers |
|
| Electrical- Capacitors |
|
| Electrical- Panel Boards |
|
| Electrical- Testing |
|
| ||
| Condensing |
|
| Control/ Display Board |
|
| Controls |
|
| Drains |
|
| Fixtures |
|
| Humidifier |
|
| Equipment |
|
| Leakage Test |
|
| Sheet Metal |
|
| TACO Pumps |
|
| Test, Adjust & Balance Report |
|
| Valves |
|
Clinical Building- Medical Genetics Lab, #898-3441, ca. 1989 |
| |
| General & Index |
|
| Sub Contractor/ Supplier |
|
| AMSCO Medical Equipment |
|
| ARCO Glass |
|
| A & S Industries Vertical Blinds |
|
| Berline Construction- Metal Framework, Drywall, Ceilings |
|
| Cardinal Fence |
|
| Certified Flooring |
|
| Contract HDW- Finish Hardware |
|
| Creative Enterprises- Caulking/ Sealant |
|
| Kloeppel, Harry J.- Fume Hoods & Furniture |
|
|
| |
| Schricker Co.- Metal Partitions & Accessories |
|
| H. Sims Painting |
|
| Wilson Partenheimer- Folding Walls |
|
| ||
| Index |
|
| Sublist |
|
Science & Engineering Tech. Phase III, #903-3602, ca. 1990 |
| |
| Clock System |
|
| Intercom System |
|
| Card Access System |
|
| Dry Type Transformers |
|
| BRK Time Switches |
|
| Hi Volt Switch & Transformer |
|
| Switchboards |
|
| Lighting |
|
| Lighting Fixtures |
|
| Lutron Systems |
|
| Lutron Wall Box |
|
| Emergency Lighting |
|
| Relay Panel |
|
| Wiring Devices |
|
| Cable Tray |
|
| Bus Duct Riser |
|
| Isoduct |
|
| Lighting Contractors |
|
| Panel Boards |
|
| Centrifugal Fans |
|
| SP Exhaust Fans |
|
| Centrifugal Inline |
|
| VAV- Fan Powered |
|
| VAV Cooling |
|
| Adjustable Pitch Standard Fan |
|
| Adjustable Pitch Compax Fan |
|
| Introduction (Contents) |
|
| Motor Controllers & Safe Switches |
|
| Fire Alarm System |
|
Medical Research & Library- Medical Genetics Office, #903-3608, ca. 1990 |
| |
| Index |
|
| Building Insulation |
|
| Sealants |
|
| Access Doors & Panels |
|
| Gypsum Drywall |
|
| Quarry Tile & Brick Pavers |
|
| Acoustical Ceiling |
|
| Painting & Finishing |
|
| Louver Blinds |
|
| Division 15- Mechanical |
|
| Sprinkler System |
|
| Division 16- Electrical |
|
Business/ SPEA- 4th Floor Remodel & Renovation, #904-3609, ca. 1990 |
| |
| Index |
|
| Architectural Woodwork |
|
| Flush Wood Doors |
|
| All Glass Entrances |
|
| Gypsum Drywall |
|
| Acoustical Ceiling |
|
| Resilient Flooring/ Carpeting |
|
| Painting/ Wall Coverings |
|
| Mechanical |
|
| Electrical |
|
| ||
| Index & Valve Tag Chart |
|
| Valve Tag Chart |
|
| Expansion Joint |
|
| Valves/ Fittings |
|
| Insulation |
|
| Inertia Frames |
|
| Animal Drinking |
|
| Floor Drain |
|
| Faucet/ Hose Reel |
|
| Pumps |
|
| Traps |
|
| Condensate |
|
| Pressure Gauge |
|
| Coil |
|
| Humidifier |
|
| Air Handling |
|
| Grills/ De-fuser |
|
| Filters |
|
| Balance Reports |
|
| ||
| Contractor’s Guarantee |
|
| Mechanical |
|
| Electrical |
|
| ||
| Index |
|
| Temperature Control- Section 1 |
|
| Pipe Insulation- Section 2 |
|
| Air Distribution- Section 3 |
|
| Plumbing Fixtures- Section 4 |
|
| Air Distribution Tests- Section 5 |
|
| Mechanical Work- Section 6 |
|
Psychiatric Research- Molecular Neurobiology Lab, #909-3771, ca. 1990 |
| |
| General |
|
| Index | 5 |
| Valve Tag Chart |
|
| Valves |
|
| Sleeve Seal |
|
| Backflow Preventer |
|
| Vacuum Pump |
|
| Fittings |
|
| Water Main |
|
| PRV & Traps |
|
| Hydronics |
|
| Air Handling Unit |
|
| Duct Coating |
|
| Air Distribution |
|
| Temperature Control |
|
| Balance Testing |
|
| Thermometer Gauges |
|
Lab Animal Facility Renovation- Riley Research, #912-3709, ca. 1991 |
| |
| General |
|
| Mechanical |
|
| Adjusting & Balancing |
|
| Labeling & Identification |
|
| Josam Company- Restroom Equipment |
|
| Water Heaters |
|
| Water Softener |
|
| Restroom Fixtures |
|
| Hydronic Piping System |
|
| Hydronic Pumps |
|
| Thermometers |
|
| Gauges |
|
| Shell & Tube Converter |
|
| Hot Water Booster Coil |
|
| Air Distribution |
|
| Humidifiers |
|
| Air Handling Unit |
|
| Centrifugal Fan |
|
| Utility Set Exhaust Fans |
|
| Low Pressure Ductwork |
|
| Special Ductwork |
|
| Ductwork Accessories |
|
| Registers, Grills, Diffusers |
|
| Air Filters |
|
| Johnson Controls- Environmental Control System |
|
| Balance Report |
|
| Adjusting/ Balancing |
|
Pathology/ Development Offices Renovation, #922-4138, ca. 1992 |
| |
| Index |
|
| Vendors |
|
| Manuals |
|
| Heads |
|
| Valves |
|
| Electrical Switches |
|
| NFPA, 13A |
|
| Warranties |
|
| Map |
|
| ||
| Laboratory Finishings |
|
| Project Manual 1 |
|
| Project Manual 2 |
|
| Index- Book 1 |
|
| Contractor/ Supplier List |
|
| Glenroy Construction Co., Inc. Guarantee |
|
| Kitchen Materials/ Equipment |
|
| Terrazzo |
|
| Glass & Glazing & Aluminum Curtain Wall |
|
| Elastic Sheet Roofing |
|
| Ceramic Tile |
|
| Marker Boards, Tack Boards & Display Cases |
|
| Metal Roof & Sheeting |
|
| Darkroom Doors |
|
| Epoxy Flooring |
|
| Plaster, Drywall & Panels |
|
| Material Processing Equipment |
|
| Lawn Irrigation |
|
| Waterproofing/ Sealants |
|
| Siding |
|
| Processing Equipment & Fume Hoods |
|
| Resilient Flooring & Carpeting |
|
| Sewer Collection System |
|
| Louvers |
|
| Material Processing Equipment |
|
| Overhead Coiling Doors |
|
| Elevators |
|
| Material Processing Equipment |
|
| Scissors Lift & Dock Levelers |
|
| Toilet Partitions |
|
| Landscape |
|
| Lockers, Fire Extinguishers |
|
| Epoxy Coating, Operable Wall, Toilet & |
|
| Corner Guards |
|
| Flush Wood Doors |
|
| Projection Screens |
|
| Index |
|
| Adjustable |
|
| Valves |
|
| Mechanical Insulation |
|
| [Section 4, empty, on file in Fire Protection Services Office] |
|
| Centrifugal Pumps |
|
| Pumping Systems | 6 |
| Plumbing Equipment |
|
| Submersible Pumps |
|
| Sewer Pumps |
|
| Acid Neutralization Tanks |
|
| Pumps |
|
| Water Softener |
|
| Vacuum Systems & Compressors |
|
| R.O. Unit |
|
| Pump Controls |
|
| Re-pressurization Pumps |
|
| HPS |
|
| TLS 1 & 2 |
|
| UV Light |
|
| Industrial Units- Water Treatment |
|
| Installation- Constant Conductivity/ Resistivity Sensors |
|
| Restroom Fixtures |
|
| Centrifugal Pumps |
|
| Badger Meter |
|
| Vented Condensate Units |
|
| Cooling Tank, Valves & Fittings, Temperature Regulators |
|
| Chemical Shot Feeder |
|
| Air Systems |
|
| Vulcan Fin Tube |
|
| Hydronic Cabinet Unit Heaters |
|
| Chilled Water Coils |
|
| Air Handling Units |
|
| Ventilation |
|
| APEX Industries, Inc. (Correspondence re: materials) |
|
| Fire Dampers |
|
| Air Volume Boxes with Hot Water Coil |
|
| Grills & Registers |
|
| [Air Filters- empty] |
|
| HVAC System |
|
| Adjusting & Balancing |
|
| Laboratory Fume Hoods |
|
| Warranties |
|
| Carbon Dioxide |
|
| Chilled Water |
|
| De-ionized Water |
|
| Domestic Water |
|
| Heat Recovery |
|
| Heating Water |
|
| High Pressure Air Lab |
|
| Lab Air |
|
| Lab Vacuum |
|
| Low Pressure Steam/ Condensate |
|
| Medium Pressure Steam/ condensate |
|
| Natural Gas |
|
| Nitrogen |
|
| Perimeter Hot Water |
|
Coleman Hall HVAC Remodel, #926-4231, ca. 1992 |
| |
| Sheet Metal |
|
| Unit Heater, HW Coils |
|
| Hot Water Specialties |
|
| Insulation |
|
| Temperature Controls |
|
| Balance |
|
| Valve Charts |
|
| Air Cooled Fluid Coolers |
|
Business/ SPEA- Rooms 2001 & 2003, #933-4495, ca. 1993 |
| |
| Index |
|
| General |
|
| Vendors |
|
| Info & Maintenance |
|
| Warranties |
|
Riley Research & Medical Science Remodel, #936-4543, ca. 1993 |
| |
| General |
|
| Vendors |
|
| Info & Maintenance |
|
| Warranties |
|
| ||
| Fire Protection |
|
| Index- Part 1 |
|
| Directories |
|
| Casework |
|
| Hollow Metal Doors & Hardware |
|
| Glass Glazing |
|
| Flooring |
|
| Painting & Vinyl Wall Covering |
|
| Fire Extinguishers & Cabinets |
|
| Signs |
|
| Plumbing/ HVAC |
|
| Electrical |
|
| Electric Fire Protection |
|
| Warranties |
|
| Index- Part 2 |
|
| Air Handling Units |
|
| Plumbing Fixtures |
|
| Ventilation Test Reports |
|
| Sprinkler Fixtures |
|
| Sprinkler System |
|
| Controls |
|
| Fire Protection Sprinkler System |
|
SET (Science & Engineering Tech.) III, #1022-0073, 1994 |
| |
Clinical Building- Chilled Water Service, #1567, ca. 1990 |
| |
| General & Index |
|
| Badger Meter |
|
| Temperature Controls |
|
| Valve Tag Charts |
|
| ||
University Hospital- Remodel & Alterations, #8311-1693, ca. 1983 |
| |
Fesler Hall- Nephrology Research & Faculty Offices, #9210-4340, ca. 1992 |
| |
| General |
|
| Pipe |
|
| Sprinklers |
|
| Fittings |
|
| Hangers |
|
| NFPA 13A |
|
| Warranties & Maintenance |
|
| Index |
|
| Electrical Switches, Dimmers & Outlets |
|
| Electrical Safety Switches & Fuses |
|
| Electric Panel Boards |
|
| Magnetic Starters |
|
| Light Fixtures |
|
| Fire Protection Equipment |
|
| Electric Wiring |
|
IU Hospital- Clinical Cancer Center, #9212-4394, ca. 1992 | 7 | |
Medical Science- Auditorium Renovation, #9511-5209, ca. 1995 |
| |
| Index |
|
| Project Phone Directory |
|
| Warranty |
|
| Hollow Metal Frames & Wood Doors |
|
| Acoustical Ceiling Systems |
|
| Resilient Tile Flooring & Carpeting |
|
| Painting & Wall covering |
|
| Pipe & Duct Insulation |
|
| Fan Coil Unit |
|
| Grilles, Registers, Diffusers, etc. |
|
| Temperature Controls |
|
| Test & Balance Report |
|
| Sound System Description |
|
| Sound System Equipment Information |
|
| Index |
|
| Devices |
|
| Panels |
|
| Fixtures |
|
| Dimming |
|
Old Library- Installation Manual, #CTS-89238-39 |
| |
| General |
|
| Mechanical |
|
| Electrical |
|
| Fixtures |
|
| Schematics |
|
| ||
| Index |
|
| Project Phone Directory |
|
| Wurster Construction |
|
| Glass Handrail |
|
| Custom Casework |
|
| Roofing System |
|
| Doors/ Frames & Hardware |
|
| Overhead Coiling Doors |
|
| Power Door Operations |
|
| Ceramic Tile |
|
| Acoustical Ceiling/ wall Systems |
|
| Flooring Systems |
|
| Painting |
|
| Visual Display Boards |
|
| Corner Guards |
|
| Metal Lockers |
|
| Toilet Accessories |
|
| Projection Screens |
|
| Entry Mats |
|
| Electronic Traction Elevators |
|
Riley Children’s Hospital #4, #C38332 |
| |
| ||
Rotary Building- Lab Renovation, ca. 1990 |
| |
| General |
|
| Electrical Panel Boards & Switches |
|
| Light Fixtures |
|
| Electrical Lamps (Bulbs) |
|
| Switches & Outlets |
|
| Raceway Systems |
|
Gross Anatomy Lab Renovation, ca. 1996 |
| |
| Warranty |
|
| Pumps |
|
| Sheet Metal |
|
| Plumbing Fixtures |
|
| Insulation |
|
| Hydronic Specialties |
|
| HVAC Equipment |
|
| Temperature Control |
|
| Water Treatment |
|
| Acid Waste |
|
| Water Purification |
|
| Balancing |
|
| Valve Tags |
|
Medical Research, #CT-SPM-58734-5 |
| |
| Index |
|
| Mechanical |
|
| Electrical |
|
| Fixtures |
|
| Drawings & Schematics |
|
Lecture Hall- Electronic Classroom Renovations, ca. 1990 |
| |
| Index |
|
| Vendors List |
|
| Valve Tag Chart |
|
| Test, Adjust & Balance Report |
|
| Air Handling |
|
| Pumps |
|
| Humidifiers |
|
| Insulation |
|
| Sheet Metal Accessories |
|
| Pipe, Valves & Fittings |
|
| Chemical Treatment |
|
8 | ||
Business/SPEA Manuals- Mechanical, ca. 1995 |
| |
Dover Elevator Owner’s |
| |
School of Dentistry Manuals- No Number |
| |
| Index |
|
| Supply Fans |
|
| Return Fan |
|
| Diffuser & Grille Test Reports |
|
| Exhaust Fans |
|
| Exhaust Grille Test Reports |
|
| Pumps |
|
| Reheat Coils |
|
| Cooling Coils |
|
| Cooling Tower |
|
Clinical Building |
| |
| Index |
|
| Piping Specialties |
|
| Domestic Water Distribution Piping |
|
| Compressed Air Systems |
|
| Index- Lab Vacuum |
|
| Vacuum Insulated Piping System |
|
| Bayonet Assembly |
|
| Field Pressure/ Leak Check Procedure |
|
| Vacuum Insulated LN2 Piping |
|
| Cryogenic Glove Valves |
|
| Vacuum Seal off Valves & Operators |
|
| Natural Gas Systems |
|
| Air Handling Units |
|
| Test, Adjust & Balance Reports |
|
| Temperature Control Systems |
|
| Polypropylene Piping |
|
Visitor’s Parking Ramp- IU Medical Center, #87094.30 |
| |
| ||
Long Hospital- Outpatient Clinic, ca. 1973 |
| |
| ||
| Fire Protection |
|
| Sound System |
|
| Fire Alarm Control Panels |
|
| Table of Contents & Adjustable |
|
| Valves |
|
| Mechanical Insulation |
|
| Fire Protection Manual Index |
|
| Zone Chart- Fire Protection |
|
| Sprinklers |
|
| Valves |
|
| Electrical Switches |
|
| Miscellaneous |
|
| Fire Pump |
|
| NFPA 13A |
|
| Maintenance Schedule |
|
| Pumps |
|
| Pumping System |
|
| Fire/ Pumping Accessories |
|
| Submersible Pumps |
|
| Sewage Ejectors |
|
| Acid Neutralization Tanks |
|
| Water Heater |
|
| Water Softeners |
|
| Vacuum Systems & Compressors |
|
| R.O Unit |
|
| Pump Controls |
|
| Re-pressurization Pumps |
|
| HPS |
|
| TLS 1 & 2, Industrial Pressure Switches |
|
| UV Light |
|
| Resistivity Mon. |
|
| Conductivity/ Resistivity Sensors |
|
| Plumbing Fixture & Trim |
|
| Hydronic Pumps |
|
| Badger Meter |
|
| Vented Condensate Units |
|
| Cooling Tank, Valves & Fittings, Thermometer |
|
| Water Treatment |
|
| Valves |
|
| Vulcan Fin Tube |
|
| Hydronic Cabinet Unit Heaters |
|
| Chilled Water Coils |
|
| Air Handling Units |
|
| Fan/ Ventilation |
|
| APEX Industries (Correspondence) |
|
| Fire Damper |
|
| Air Volume Boxes with Hot Water Coil |
|
| Grilles & Registers |
|
| APEX Industries- Filters |
|
| HVAC Systems |
|
| Adjusting & Balancing Report | 9 |
| Laboratory Fume Hoods |
|
| Warranties |
|
| Valve Tag Lists [to be provided upon completion] |
|
| ||
| General |
|
| Cable |
|
| L.V. Busway |
|
| Cable Tray |
|
| Cable Insulation |
|
| Safety Switches & Circuit Breakers |
|
| Caterpillar Generator Set |
|
| Short Circuit & Overcurrent Protective Device Coordination Study- Table of Contents |
|
| Short Circuit… Introduction |
|
| Short Circuit… Summary |
|
| Short Circuit… Calculations |
|
| Short Circuit… Coordination |
|
| Circuit Breakers |
|
| Switchgear |
|
| Load Interrupter |
|
| Switchgear Test |
|
| Low Voltage Switchgear |
|
| Electric Transformers/ Panel Boards |
|
| Distribution Panel Boards |
|
| Normal Low- Electric Circuits |
|
| Normal High- Electric Circuits |
|
| Emergency Low- Electric Circuits |
|
| Emergency High- Electric Circuits |
|
| Lab Basement- 4th Floors- Electric Circuits |
|
| Low Volt MCC (Motor Control Centers) |
|
| Light Fixtures |
|
| Light Bulbs |
|
| Lightning Protection |
|
| Sound System |
|
| Cable |
|
| Door Security/ Card Access System |
|
| Lutron Dimming System |
|
Medical Information Sciences Building – O + M Manuals 8/2005 |
| |
| Contractor Subcontractor and Material Supplier List |
|
| Statement of Warranty |
|
| Testing & Proof of Performance |
|
| Valves |
|
| Piping Specialties |
|
| Expansion Compensation |
|
| Meters and Gauges |
|
| Supports and Anchors |
|
| Mechanical Identification |
|
| Vibration Control |
|
| Mechanical Insulation |
|
| Fire Protection Sprinkler System |
|
| Fire Pumps |
|
| Standpipe and Hose Systems |
|
| Domestic Water Distribution Piping |
|
| Drainage and Vent Systems |
|
| Interceptors |
|
| Fixtures |
|
| Sewage and Sump Pumps |
|
| Domestic Water Pumps |
|
| Water Softeners |
|
| Instantaneous Steam Water Heater |
|
| Natural Gas Systems |
|
| Hydronic Piping |
|
| Hydronic Specialties |
|
| Steam and Condensate Piping |
|
| Med/High Pressure Steam Supply and Condensate Return |
|
| Variable Volume Terminal Units |
|
| HVAC Pumps |
|
| Chemical Treatment Systems |
|
| Split System Outdoor Heat Pump Units |
|
| Indoor Heat Pump System |
|
| Heat Exchanger – Shell and Tube |
|
| Intergral Face and Bypass Coil |
|
| Humidifiers |
|
| Terminal Units |
|
| Air Handling Units |
|
| Variable Air Volume – Custom Air Handling Unit |
|
| Centrifugal Fan |
|
| Exhaust Fans |
|
| Low Pressure Ductwork |
|
| High Pressure Ductwork |
|
| Flexible Ductwork |
|
| Buried Ductwork |
|
| Prefabricated Insulated Plenum Panels |
|
| Ductwork Accessories |
|
| Sound Attenuators |
|
| Variable Volume Terminal Units |
|
| Diffusers, Registers and Grilles |
|
| Roof Vents |
|
| Adjusting and Balancing |
|
Medical Information Sciences Building – Duct Testing 2/14/2006 | 10 | |
| Basement North |
|
| 1st Floor North |
|
| 1st Floor South |
|
| 2nd Floor North |
|
| 2nd Floor South |
|
| 3rd Floor North |
|
| 3rd Floor South |
|
| 4th Floor |
|
| 5th Floor |
|
Medical Information Sciences Building – O + M Telecommunication11/2007 |
| |
| Conduit |
|
| Insulation |
|
| Warranty |
|
Medical Information Sciences Building – O+M Electrical Volume 1 7/2007 |
| |
| Basic Electrical Materials and Methods |
|
| Overcurrent Protective Device Coordination |
|
| Grounding and Bonding |
|
| Electrical Identification |
|
| Testing (includes CD) |
|
| Conductors and Cables |
|
| Medium-Voltage Cables |
|
| Raceways and Boxes |
|
| Cable Trays |
|
| Wiring Devices |
|
| Lighting Control Devices |
|
| Enclosed Switches and Circuit Breakers |
|
| Fuses |
|
Medical Information Sciences Building – O+M Electrical Volume 2 11/2005 |
| |
| Packaged Engine Generators (includes CD) |
|
| Transfer Switches |
|
Medical Information Sciences Building – O+M Electrical Volume 3 5/2005 |
| |
| Medium Voltage Switch – MVS – MSA |
|
| Power Transformers – UTR – OTX |
|
| Low Voltage Switchgear – LVA |
|
| Switchboards – SUS |
|
| Busway – BUS |
|
| Motor Control Centers – FVC |
|
| Panelboards – SUP |
|
| Dry Type Transformers – DTT |
|
| Shop Drawings |
|
Medical Information Sciences Building – O+M Electrical Volume 4 1/2006 |
| |
| Interior Lighting |
|
| Exterior Lighting |
|
| Dimming Controls |
|
Medical Information Sciences Building – O+M Electrical Volume 5 10/2005 |
| |
| Lighting Protection |
|
| Fire Detection and Alarm System – Addressable |
|
| Public Address and Music Equipment |
|
| Voice and Data Communication Cabling (includes CD) |
|
Medical Information Sciences Building – O+M 9/1/2005 |
| |
| Termite Control |
|
| Water Distribution |
|
| Sanitary Sewerage |
|
| Storm Drainage |
|
| Stone Paving – Bluestone |
|
| Irrigation Systems |
|
| Lawns & Grasses |
|
| Exterior Plans |
|
| Thermoplastic Sheet Waterproofing |
|
| Vertical Metal Wall Panel Cladding |
|
| Insulated Metal Wall & Soffit Panels |
|
| EPDM Membrane Roofing – Ballasted |
|
| Roof Expansion Assemblies |
|
| Sprayed Fire – Resistive Materials |
|
| Joint Sealers |
|
| Flush Wood Doors |
|
| Overhead Coiling Doors |
|
| Aluminum-Framed Entrances & Stormfronts |
|
| Metal-Framed Skylights |
|
| Door Hardware – Scheduled |
|
| Automatic Door Operators |
|
| Glazing |
|
| Self-Opaqueing Glass |
|
| Decorative Plastic Glazing |
|
| Glazed Curtain Wall |
|
| Ceramic Tile |
|
| Dimension Stone Tile |
|
| Acoustical Panel Ceilings |
|
| Metal Specialty Ceilings |
|
| Resilient Floor Tile |
|
| Resinous Flooring Mezzanine Waterproofing |
|
| Carpet |
|
| Carpet Tile | 11 |
| Interior Stone Facing |
|
| Acoustical Wall Panels |
|
| Sound Control Wall & Ceiling Panels |
|
| Painting |
|
| High Performance Coatings Aliphatic Polyurethane |
|
| Visual Display Surfaces |
|
| Directory Display Cases |
|
| Impact-Resistant Wall Protection |
|
| Corner Guards – Stainless Steel |
|
| Access Flooring |
|
| Flagpoles |
|
| Building Signs |
|
| Metal Lockers |
|
| Solid Phenolic Lockers |
|
| Postal Specialties |
|
| Toilet and Bath Accessories |
|
| Window Cleaning Equipment |
|
| Projection Screens |
|
| Loading Dock Equipment |
|
| Kitchen Equipment Appliances |
|
| Roller Shades |
|
| Floor Slab Jack-up System |
|
| Glazed Entry Canopy Structures |
|
| Electric Traction Elevators Passenger and Service |
|
| Electric Trolley Hoists |
|
Medical Information Sciences Building – Painting 2/22/2007 |
| |
Medical Information Sciences Building – Thyssenkrupp Elevator Owner’s Manual 3/16/2006 |
| |
Medical Information Sciences Building – Rainbird Irrigation – Warranties 2/27/2007 |
| |
Medical Information Sciences Building – Contract Hardware & Specialties 5/23/2007 |
| |
| IUPUI Med Info Sciences BLDG |
|
| IUPUI Med Info Sciences BLDG 1st Floor |
|
| IUPUI Med Info Sciences BLDG 2nd Floor |
|
| IUPUI Med Info Sciences BLDG 3rd Floor |
|
| IUPUI Med Info Sciences BLDG 4,5,6,7th Floor |
|
Business/SPEA Renovation of BS2000 – O + M Manual 9/12/2006 |
| |
| Ornamental Metals |
|
| Door Hardware |
|
| Gypsum Wall Assemblies |
|
| Acoustical Ceilings |
|
| Flooring |
|
| Paint |
|
| Visual Display Surfaces Projection Screens |
|
| System Furniture |
|
| Mechanical |
|
| Electrical |
|
Business/SPEA Renovation – O + M Manual 9/1/2006 |
| |
| Steam Coil |
|
| Pumping Trap |
|
| Float Steam Traps |
|
| Relief Valves |
|
| Steam Reducing Valve |
|
| Flash Tank/ Condensate Cooler |
|
| Steam Accessories |
|
| VAV Box FCV |
|
| VAV Boxes |
|
| Test & Balance |
|
Engineering Technology Building – Existing Basement Renovation 11/17/2005 |
| |
| Directory |
|
| Finish Schedule |
|
| Division 3 Concrete |
|
| Division 4 Masonry |
|
| Division 5 Metal Fabrications |
|
| Division 7 Joint Sealants |
|
| Division 8 Doors Frames & Hardware Glazing |
|
| Division 9 Gypsum Wall Assemblies Acoustical Ceilings |
|
| Division 9 Flooring Paint |
|
| Division 10 Specialties |
|
Engineering Technology Building – Existing Basement Renovation 8/4/2005 |
| |
| General |
|
| Cellular Floor Raceway |
|
| Panel Boards |
|
| Lighting |
|
| Fire Alarm |
|
Engineering Technology Building – Existing Basement Renovation 4/19/2007 |
| |
| Valves |
|
| Piping Specialties |
|
| Supports and Anchors |
|
| Mechanical Identification |
|
| Mechanical Insulation |
|
| Wet Pipe Sprinkler System |
|
| Domestic Water Distribution Piping |
|
| Soil and Waste Systems |
|
| Plumbing Fixtures |
|
| Hydronic Piping |
|
| Water Treatment Systems |
|
| Electrode Steam Generating Humidifiers |
|
| Centrifugal Fans |
|
| Ductwork Accessories |
|
| Air Outlets and Inlets |
|
| Air Terminals |
|
| Temp Control Systems/ Sequence of Operation |
|
Campus Center Operation & Maintenance Manual Vol. 1 of 3. Index-15060 | 12 | |
| Index |
|
| Vendor List |
|
| Service & Maintenance Schedule |
|
| 15020 Comp. & Start Up |
|
| 15021 |
|
| 15025 |
|
| 15030 |
|
| 15060 |
|
Campus Center Operation & Maintenance Manual Vol. 1, File 2 15160-15230 |
| |
| 15160 |
|
| 15165 |
|
| 15170 |
|
| 15180/15190 |
|
| 15230 |
|
Campus Center Operations & Maintenance Manual Vol. 1, File 3 15235-15253 |
| |
| 15235 |
|
| 15253 |
|
Campus CenterOperations & Maintenance Manual Vol. 1 File 4, 15265-15420 |
| |
| 15265 |
|
| 15285 |
|
| 15305 |
|
| 15306 |
|
| 15315 |
|
| 15405 |
|
| 15412 |
|
| 15420 |
|
Campus Center Operations & Maintenance Manual Vol. 2 of 3, File 1, Index-15510 |
| |
| Index |
|
| 15421 |
|
| 15422 |
|
| 15424 |
|
| 15427 |
|
| 15510 |
|
Campus Center Operations & Maintenance Manual Vol. 2 of 3, File 2 15701-15703 |
| |
| 15701 |
|
| 15702 |
|
| 15703 |
|
Campus Center Operations & Maintenance Manual Vol. 2, File 3. 15710 | ||
| 15710 |
|
Campus Center Operations & Maintenance Manual Vol. 2, File 4. 15735-15750 |
| |
| 15735 |
|
| 15736 |
|
| 15740 |
|
| 15742 |
|
| 15750 |
|
Campus Center Operations & Maintenance Manual Vol. 3, File 1. Index-15846 |
| |
| Index |
|
| 15760 |
|
| 15765 |
|
| 15780 |
|
| 15820/15830 |
|
| 15840-15846 |
|
Campus Center Operations & Maintenance Manual Vol. 3, File 2, 1580-15895 |
| |
| 15850 |
|
| 15860/15861 |
|
| 15870 |
|
| 15876 |
|
| 15895 |
|
Operation & Maintenance Manual, Vol. 1, File 1. Table of Contents-Cabinets. IUSD Endodontics Room #306 |
| |
| Certificate of Warranty |
|
| Project Directory |
|
| Cabinets |
|
Operation & Maintenance Manual, Vol. 1, File 2, Thermal Protection- Electrical, IUSD Endodontics Room 306 |
| |
| Thermal & Moisture Protection |
|
| Finishes |
|
| Specialties |
|
| Plumbing |
|
| Electrical |
|
Operation & Maintenance Manual IUSM Riley Research Room 140. File 1, 1-5 |
| |
Operation & Maintenance Manual IUSM Riley Research Room 140 File 2, 1-10 & 1-5 |
| |
Operation & Maintenance Manual File 1, Index-Plumbing , Riley Research Third Floor Renovation |
| |
Operation & Maintenance Manual File 2, HVAC-10, Riley Research Third Floor Renovation |
| |
| HVAC |
|
| 10 |
|
Special Projects Warranties for IUPUI Tunnel Repairs Phase II |
| |
| Index |
|
| Lawns |
|
| Deck Waterproofing Membrane |
|
| Expansion Joint Sealing Systems |
|
| Elastometric Joint Sealants |
|
| Cementitious Crystalline Waterproofing |
|
| Window |
|
Operation & Maintenance File 1, General - 16470 PDU-3, Communication Technology Complex-ICTC 024 Supplemental Cooling |
| |
| General |
|
| 16200 Panelboard |
|
| 16200 Disconnects |
|
| 16200 Encl. Switch |
|
| 1625 ATS |
|
| 16280 RDC “H” |
|
| 16470 PDU-3 |
|
Operation & Maintenance File 2, 16612 “C”- Flywheel UPS FBO |
| |
| 16612 UPS “C” |
|
| 16613 Flywheel UPS “C” |
|
| Flywheel UPS FBO |
|
Operation & Maintenance Manual, File 3, Schematic Communication Technology Complex - ICTC 024 Supplemental Cooling |
| |
Operation & Maintenance Manual Engineering Science & Technology Building Project #20063486 HVAC Updgrades for Wet Labs Phase I, Job #2717, Sept 2007 | 13 | |
University Hospital Parking Garage Emergency Repairs to Northwest Stairwell Project 20063536 Product Submittals 3/26/2007 |
| |
Electrical Operation & Maintenance Manual, Division 16, Cavanaugh Hall, n.d. |
| |
| Fuses |
|
| Transformers |
|
| Engineering Reports |
|
| Warranty |
|
Project 20051999 Engineering & Technology Building 3rd Floor Renovations |
| |
| Warranty |
|
| Panel Directories |
|
| Devices & Plates |
|
| Light Fixtures |
|
| Lamps |
|
| Cable Supports |
|
| V/D Devices, Plates |
|
| Patch Panel/Cable Mgement |
|
| Test Reports |
|
| Electrical |
|
Project 20052098 Operation & Maintenance Manual, Emerson Hall, 5th Floor Renovation File 1, A-I |
| |
Project 20052098 Operation & Maintenance Manual, Emerson Hall, 5th Floor Renovation File 2, J-S |
| |
Operation & Maintenance Manual Emerson Hall Lighting, 11/7/2007 |
| |
Maintenance Manual Emerson Hall 5th Floor Renovation Project 20052098 Mechanical Work Completed 2007 |
| |
| Plumbing Fixtures |
|
| Sheet Metal |
|
| Sheet Metal I, O & M |
|
| Carrier Air Handling Unit |
|
| Carrier AHU I, O & M |
|
Instruction Manual SEL-2030 Communications with CD 9/52007 |
| |
Manual Project 20063236 Substation B Replacement, File 1 Operation & Maintenance , n.d. |
| |
Project 20063236 Operation & Maintenance Manual Substation B Replacement, File 2, Section 5, n.d. |
| |
Project 20063236 Operation & Maintenance Manual Substation B Replacement , File 3 Sections 6-8 |
| |
Operations & Maintenance Manual Law School IUPUI # 87-4-238, 3/15/1988 File 1 |
| |
| Plumbing Fixtures |
|
| Floor Drain |
|
| Heat & Cool Equipment |
|
| Grill Diff Extractors |
|
| Damper Fans |
|
| Temp Controls |
|
| Balance Report |
|
| Valve Tag |
|
| Fire Alarm System |
|
| Wiring Devices |
|
| Panelboard Fuses |
|
Operations & Maintenance Manual Law School IUPUI # 87-4-238, 3/15/1988 File 2 |
| |
| Lighting Controls |
|
| Wood Doors & HDWR |
|
| Resilient Flooring |
|
| Carpet |
|
| Wallcovering |
|
Project Manual Law School Test, Adjust, & Balance Report, 5/7/2001 | ||
Specs. Law School IUPUI# 6505, 3/15/1968 [2 folders] |
| |
Specs Law School (Bid Set) IUPUI# 6505, 3/15/1968 [2 folders] |
| |
Ransburg Building Remodeling Equipment Installation/Operation Instructions Mechanical, 12/8/1966 |
| |
Mary Cable School Building Feasibility Study 6/20/1991 |
| |
Specs for Mechanical & Electrical Systems for Mary Cable School, IUPUI# 8572187, 10/25/1985 |
| |
Maintenance Manual for the Mary Cable Building Electrical Renovations- IUPUI School of Music #997-6187, 2000 | 14 | |
Operational & Mechanical Mary Cable, n.d. |
| |
| Elec/Boiler |
|
| Mech/Elec. Specs (10/25/1985) |
|
| Electrical Renovations ((8/24/2000) |
|
Project Manual Mary Cable Building Demolition IU Project #20051667, 6/2005 | ||
Law School Energy Audit 6/15/1995 |
| |
Operational & Mechanical Manual Law School Mechanical Systems 5/13/1971 (File 1) |
| |
| Temp Control |
|
| Chiller |
|
| Instruction Book Trane Air Condition |
|
| Cooling Tower |
|
Operational & Mechanical Manual Law School Mechanical Systems 5/13/1971 (File 2) |
| |
| HTG & Vent Units |
|
| Auto Filters |
|
| Pumps |
|
| Fans |
|
| Venilators |
|
| Meter |
|
| Heating Specialties |
|
| Flush Valves |
|
| Water Coolers |
|
| Pressure Vessel Data |
|
| Electrical Blue Prints |
|
Mechanical & Electrical Specifications for Law School 3/15/1968 |
| |
Specification for Mechanical & Electrical for Law School 10/23/1967 |
| |
Law School Project # 2-5-00140-0 Primary Switchgear |
| |
Law School Project # 2-5-00140-0 Lighting Fixtures |
| |
Law School Project # 2-5-00140-0 Motor Controls |
| |
Law School Project # 2-5-00140-0 Capacitors 5/14/1969 |
| |
Law School Project # 2-5-00140-0 Motorized Dimmers 5/14/1969 |
| |
Law School Project # 2-5-00140-0 Cable Tray 5/14/1969 |
| |
Law School Project # 2-5-00140-0 Sound Systems 5/14/1969 |
| |
Law School Project # 2-5-00140-0 Panel Boards 3/5/1969 |
| |
Law School Project # 2-5-00140-0 Bus Duct 3/10/1969 |
| |
Law School Project # 2-5-00140-0 Secondary Switchboard 3/10/1969 |
| |
Law School Project # 2-5-00140-0 Dry Type Transformers 3/10/1969 |
| |
Law School Project # 2-5-00140-0 Primary Transformers 3/10/1969 |
| |
Law School Project # 2-5-00140-0 Motorized Dimmers 12/7/1970 |
| |
Law School Project # 2-5-00140-0 Motorized Controls 12/7/1970 |
| |
Law School Project # 2-5-00140-0 Motor Control Centers 12/7/1970 |
| |
School of Law Valve Chart 5/13/1971 |
| |
School of Law Motor Data 12/7/1970 |
| |
Central Chilled Water University Hospital System Phase II IUPUI #859-2240, 2/1986 |
| |
Project Manual for Construction or an Addition to the Indiana State Bd of Health, 8/16/1968 |
| |
O&M Manual Eyewash & Emergency Showers Installation Proj. # A70-301A |
| |
| Firestop Sealant |
|
| Starters |
|
Project Manual for Laboratory Hoods, Eye Wash, & Emergency Showers Proj. #A70-301A, 5/20/1995 |
| |
Project Manual for Laboratory Hoods, Eye Wash, & Emergency Showers Proj. #A70-301A, 3/22/1996 |
| |
Eye Wash & Emergency Shower Installation, 8/19/1996 |
| |
| Fixtures |
|
| Pump |
|
Project Manual for Mechanical Construction Addition to State Board of Health Building Proj # A70-701, 8/16/1968 |
| |
Survey and Analysis of HVAC & Electrical Systems, State Proj #A70-511/CDG Proj. # 8601, 3/23/1987 |
| |
Installation & Start up Instructions Model 214 Vertical Scale Indicator, 1/63 | 15 | |
| Model 214 Scale Indicator |
|
| Model 242 Transmitter |
|
| Model 255 Transmitter |
|
| Model 391 Primary Elements & Fittings for Fluid Measure |
|
| Model 771 Hays Integrator |
|
| Model 854 Universal Controller |
|
| Model 855 Universal Controller |
|
| Installation Operating Instructions Electrical Power Units E873/874C |
|
| Hays Control Drawings |
|
Power Plant Westinghouse Electric. Corp. Medium Voltage Switchgear, 5/14/1987 |
| |
Operational & Maintenance Manual Power Plant Substation C, 9/23/2003, File 1 |
| |
| CD-Rom |
|
| ARC Flash Data |
|
| Coordination Study |
|
| Table of Contents |
|
| Torque Table |
|
| Power Up/Down |
|
| Maint. Guide |
|
| Drawings |
|
Operational & Maintenance Manual Power Plant Substation C, 9/23/2003, File 2 |
| |
| Bill of Material |
|
| Voltage XFRMR |
|
| ABB L.I. Switch |
|
| Main Fuses |
|
| Surge Arrestors |
|
| Vacuum Switches |
|
| Reactors |
|
| Capacitor Fuses |
|
| Capacitors |
|
| Nokian A12 Controller |
|
| PLC |
|
| Relays OV, OT & Unbalance |
|
| Unbalance PT |
|
| Paint Specs |
|
| Door Locks |
|
| Exhaust Fan |
|
| PML ION 7500 |
|
Power Plant Trouble Shooting & Repair Manual Generator Sets, 1987 |
| |
Power Plant Folder 1 |
| |
| Smoke Breeching Repair, 11/12/1964 |
|
| Specs Repair Brick 11/8/1965 |
|
Power Plant Folder 2 |
| |
| Steam 10/20/1964 |
|
| Steam Generator Specs 6/25/1965 |
|
Power Plant File 3 |
| |
| Repointing and Repair of the Exterior Brick Walls, 11/8/1995 |
|
Power Plant File 4 |
| |
| Insurance Inspections, 8/4/19435/6/1966 |
|
Power Plant File 5 |
| |
| Misc., 1950-1962 |
|
Power Plant File 6 |
| |
| Install/Operating Instructions ARE Series Standby Power Charger |
|
| Stationary Battery |
|
| Specs Standby Steam Gen. 2/9/1966
|
|
Bowers Specs Project Manual, 7/28/1965 |
| |
| Roofing |
|
| Specification Alterations to Present Office |
|
| Specification for Remodel 7/28/1965 |
|
| Specification for Remodel |
|
Maintenance and Parts Manual Warthin Apartments, 3/22/1983 |
| |
Warthin Apartment Elevator Addition Operations & Maintenance, D.O. #815-1366, 1/17/1983 [2 folders] |
| |
Warthin Apartment Addition Plans |
| |
Warthin Apartment Elevator Addition | 16 | |
| Heating Equipment |
|
| Plumbing Equipment |
|
Warthin Apartments Heating, Ventilating, Plumbing, & Electrical Installations, 10/1956 |
| |
Warthin Apartments General Construction 10/8/1957 |
| |
Warthin Apartments Specs for Heating, Ventilating, Plumbing and Electrical Installations 10/1956 |
| |
Warthin Elevator IUPUI 815-1366 Change Bulletins and Change Orders 12/1982 |
| |
Warthin Elevator IUPUI 815-1366 Submittals, 1983 |
| |
Summary of Work RIS Paper Building, 3/25/2005 |
| |
Misc. Documents |
| |
Radial Brick Chimney for 1950 Power Plant Extension, 5/15/1950 |
| |
Structural Portion of Power Station Extension, 5/8/1950 |
| |
Steam Generating Units for Extension of Power Station 10/14/1949 |
| |
Miscellaneous Auxiliary Equipment and Piping System for Extension of Power Plant, 5/16/1929 |
| |
Switch Board for New Generator Unit & Changes & Additions in Wiring Systems for Extension of Power Plant 5/16/1929 |
| |
Boiler & Mechanical Stoker for Extension of Power Plant, 5/16/1929 |
| |
Remodeling of Power Plant for Riley Hospital 6/3/1929 |
| |
Report on the Advantages of Purchased Electric Power 4/7/1950 |
| |
Review & Comments on Report of Indianapolis Power & Light Company on Advantages of Purchasing Electrical Power, 3/23/1951 |
| |
Architectural Portion of 1950 Power Plant Extension Including Drainage & Plumbing System 5/15/1950 |
| |
Addition to Power House, 1950 |
| |
Additional Sub-Station Capacity & Electrical Distribution System, 5/1/1957 |
| |
Additions & Alterations to Vacuum Condensate Piping System & Installation of Ash System Air Washer, 11/16/1953 |
| |
Power Plant Reports 1928-1936 |
| |
| 1928-1931 |
|
| 1932-1934 |
|
| 1943-1936 |
|
Power Plant Reports 1942-1969 |
| |
| 1942-1950 |
|
| 1950-1951 |
|
| 1951-1952 |
|
| 1952-1953 |
|
| 1953-1954 |
|
| 1954-1955 |
|
| 1955-1956 | 17 |
| 1956-1957 |
|
| 1957-1958 |
|
| 1958-1959 |
|
| 1959-1960 |
|
| 1960-1961 |
|
| 1961-1962 |
|
| 1962-1963 |
|
| 1963-1964 |
|
| 1964-1965 | 18 |
| 1965-1966 [2 copies] |
|
| 1966-1967 |
|
| 1967-1968 |
|
| 1968-1969 |
|
School of Nursing Learning Resource Center Electrical Operation Maintenance Manual, 2008 | 19 | |
| 16510 Interior Luminaries |
|
| 16134 Cable Trays |
|
| 16272 Dry Type Transformers |
|
| 16423 Enclosed Motor Controllers |
|
| 16443 Panel Boards |
|
| 16725 Telecommunications |
|
School of Nursing Operations & Maintenance Manual , 2008 File 1 |
| |
| Case Work |
|
| Store Front |
|
| Doors Frames & Hardware |
|
School of Nursing Operations & Maintenance Manual, 2008 File 2 |
| |
| Ceramic Tiles |
|
| Gypsum Wallboard Assemblies |
|
| Acoustic Ceiling Tiles |
|
| Flooring & Paint |
|
| Cubicle Track Display Case & Boards |
|
| SS Corner Guards Operable Partitions |
|
| Project Screens |
|
School of Nursing Mechanical Operation & Maintenance Manual File 1, 2008 |
| |
| Test & Balance Report |
|
| O & M Manuals Vacuum System Split unit AC |
|
| 15075 Pipe Markers and Valve Tags |
|
School of Nursing Mechanical Operation & Maintenance Manual File 2, 2008 |
| |
| 1502 & 15086 Pipe & Duct Insulation |
|
| 15812 Coil Pak for VAV Units |
|
| 15145 & 15146 Floor Drain & Sanity Pipe & Fittings |
|
| 15145 & 15214 Copper Fittings |
|
| 15214 Med Gas Equipment |
|
| 15214 & 15145 & 15182 Valves |
|
| 15140 Plumbing Fixtures |
|
| 15725 Ductless AC Unit |
|
| 15840 Air Terminal Units |
|
| 15850 Air Outlets & Inlets |
|
Manual University Place Conference Center & Hotel Operations & Maintenance, Vol. 1, File 1 |
| |
| Table of Contents |
|
| Sublist |
|
| Warranties O&M Manuals |
|
| General Requirements |
|
| Sitework |
|
| Concrete |
|
| Masonry |
|
| Metals |
|
| Wood & Plastic |
|
| Thermal Moisture Protection |
|
| Doors & Windows |
|
| Finishes |
|
| JLCF Warranty |
|
| Carpet |
|
| Resilient |
|
| Specialities |
|
University Place Conference Center & Hotel, Operations & Maintenance Manual Vol. 1, File 2 |
| |
| Equipment |
|
| Dough Pro |
|
| Fetco |
|
| Gaylord |
|
| Hatco |
|
| Jade |
|
| Keating |
|
| Piper |
|
| Traulsen |
|
| Wells |
|
| Wittco |
|
| Furnishings |
|
l University Place Conference Center & Hotel, Operations & Maintenance Manua Vol. 1, File 3 |
| |
| Special Construction |
|
| Convey Systems |
|
| Mechanical |
|
| Plumbing Valves—Resubmittal |
|
| Hangers & Support |
|
| Mechanical Identification |
|
| HVAC Insulation |
|
| Private Water Supply Report |
|
| Food Court Redevelopment |
|
| Plumbing Fixtures |
|
| HVAC Valves- Resubmittal |
|
| Standard Testing Record Form |
|
| Meters & Gauges- REsubmittal |
|
| Hangers & Supports |
|
| Vibration Controls |
|
| Mechanical Identification |
|
| HVAC Insulation |
|
Operations & Maintenance Manual University Place Conference Center & Hotel, Operations & Maintenance Manual Vol. 1, File 4 |
| |
| Flow Control Valves-Resubmittal |
|
| Valves Pumps and Accessories |
|
| Sheet Metal Duct Construction Standards |
|
University Place Conference Center & Hotel, Operations & Maintenance Manual Vol. 1, File 5 |
| |
| Heat Exchanger |
|
| Air Handling Units |
|
| Fan Coil Units |
|
| Finned Tube Radiation |
|
University Place Conference Center & Hotel, Operations & Maintenance Manual, Vol 2.—Electrical, File 1 |
| |
| Complete Electrical |
|
| Section 260533 Raceway and Boxes |
|
| Section 260933 Central Dimming System |
|
| Section 262200 Low Voltage Transformers |
|
University Place Conference Center & Hotel, Operations & Maintenance Manual, Vol 2.—Electrical, File 2 |
| |
| Food Court Renovation 262813 Fuses |
|
| Food Court Renovation 262913 Enclosed Controllers |
|
| Warranty Section 265100 Interior Lighting |
|
| Warranty Section 271500 Communications Horizontal Cabling |
|
University Place Conference Center & Hotel, Operations & Maintenance Manual, Vol 2.—Electrical, File 3 |
| |
| Food Court Renovation 274116 AV Installation |
|
| Food Court Renovation 283111 Digital Addressable Fire Alarm System |
|
University Place Conference Center & Hotel, Operations & Maintenance Manual, Vol 3-A/V Installation, File 1 |
| |
| Product Data |
|
| Drawings |
|
| Warranty |
|
| In Service Training |
|
IUPU Columbus Center-Library Remodel Operation & Maintenance Manual, Project# IU20063051, 2008 |
| |
| Table of Contents |
|
| Operations & Maintenance |
|
| Carpet & Resilient Base |
|
| Ceramic Tile |
|
| Glass |
|
| Markerboards/Tackboards |
|
| Plumbing/HVAC |
|
| Projection Screens |
|
| Steel Frames/Wood Doors/Finish Hardware |
|
| Window Treatments |
|
| Parts & Equipment Nomenclature |
|
| Product Warranties |
|
| Atlas Flooring |
|
| Claridge Chalkboards/Markerboards |
|
| Fire Extinguisher/Products |
|
| Johnson Controls HVAC |
|
| Draper Projection Screens |
|
| Stanley Doors/Hardware |
|
| Subcontractor/Vendor Contact List |
|
| Contractor/Subcontractor Warranties |
|
| Quantum General Contractors |
|
| Certified Floor Covering Services |
|
| Claridge Products & Equipment |
|
| DL Industrial |
|
| Flawless Construction & Demolition |
|
| General Interiors |
|
| Guardian Fire Systems |
|
| Hawkins Cabinet Co |
|
| Indiana Drapery |
|
| IRC Roofing |
|
| John Ulrey’s Glass & Mirror |
|
| McCammack Tile |
|
| O’Sullivan Painting & Caulking |
|
| The Genesis Company |
|
| Testing Reports |
|
IUPU Columbus Center-West Wing Renovation Operation and Maintenance Manual, Project # IU20063050, 2008 |
| |
| Table of Contents |
|
| Carpet & Resilient Base |
|
| Ceramic Tile |
|
| Glass |
|
| Markerboards/Tackboards |
|
| Plumbing/HVAC |
|
| Projection Screens |
|
| Steel Frames/Wood Doors/ Finish Hardware |
|
| Window Treatments |
|
| Parts & Equipment |
|
| Atlas Flooring |
|
| CIH Doors/Hardware |
|
| Claridge Chalkboards/Markerboards |
|
| Johnson Controls HVAC |
|
| Draper Projection Screens |
|
| Subcontractor/Vendor Contact List |
|
| Quantum General Contractors |
|
| Certified Floor Covering Services |
|
| Claridge Products & Equipment |
|
| DL Industrial |
|
| Flawless Construction & Demolition |
|
| General Interiors |
|
| Guardian Fire Systems |
|
| Indiana Drapery |
|
| IRC Roofing |
|
| John Ulrey’s Glass & Mirror |
|
| McCammack Tile |
|
| O’Sullivan Painting & Caulking |
|
| The Genesis Company |
|
| Testing Reports |
|